Lamda Hellix Athens Data Centre Campus (ATH3 Data Centre)
(in partnership with Ecoref PC)
Duration: 2021 – Today
Engineering Scope of Services:
1. Submission of Design Work Plans:
Review of stage 4 design deliverables, preparation and submission of Design Work Plans.
2. Stage 5 design (detailed design):
- Plumbing (drainage, sewage, water supply)
- Electrical installations (MV, LV and ELV)
- Lighting and emergency lighting installations
- Security Services (access control system, intruder detection system, video surveillance system)
- HVAC installations
- Fire protection (fire alarm, fire detection, inert gas fire suppression, high pressure water mist, standpipe etc.)
- DATA – ICT
- Leakage detection system
- BMS/Controls
Deliverables:
- Updated BIM model (stage 5 design).
- Full series of plan drawings of all levels (per discipline) extracted from REVIT model
- Elevation and section drawings (per discipline) extracted from REVIT model (
- Schematics and single line diagrams.
- Coordinated services drawings extracted from REVIT model
- Equipment list
- Bill of quantities
- Technical description (per discipline)
- Finalization of stage 4 calculations, where appropriate
- Final as-built BIM model
Engineering Services for Preliminary Design – feasibility study of a new Data Center at Crete. Technical Specifications for a new Data Center for ENISA
Project’s Owner: ENISA
Duration: 2019
NMC DATA ROOM – CONTROL AND UPGRADE STUDY
Project’s Owner: WIND SA
Duration: 2013
E/M STUDY AND CONSTRUCTION SUPERVISION ON THE IMPROVEMENT OF AIR CONDITIONING /VENTILATION INSTALLATIONS FOR THE ADDITION OF NEW EQUIPMENT INTO THE IT CENTER OF GENIKI BANK AT THE HQ’S BUILDING AT MESOGION STR.
Duration: 2010
Scope of Works: Design of E/M installations Construction supervision |
PARTICIPATION AT THE FOLLOWING PROJECTS
SUPERVISION OF THE ELECTROMECHANICAL INSTALLATIONS OF THE NEW I.T. CENTER OF THE NATIONAL BANK OF GREECE, AT GERAKAS ATTIKIS
Object of supply of services: The scope of the project was the supervision and commission of the E/M installations of the project “New data processing center of National Bank of Greece at Geraka, Attiki”, until its final acceptance, that is:
Supervision of the project: It comprises the responsible monitoring of the works being executed according to the approved application design, the issue of full instructions, and the work of minor modifications to the initial design and generally the care for contractor’s compliance with his contractual obligations and the safeguarding of employer’s interests.
Commission of the project: It comprises the participation in the procedures of the committees of the temporary and final acceptance of the project and the drawing up of the relevant recommendations, in accordance with the bank’s instructions
Scope of Works: Supervision and acceptance of the project |
DESIGN AND CONSTRUCTION SUPERVISION OF THE ELECTROMECHANICAL INSTALLATIONS OF THE NEW IT CENTER OF ALPHA BANK IN SERBIA.
Scope of Works: The object of the given services includes the elaboration of the E/M installation designs and construction supervision. |
DESIGN AND CONSTRUCTION SUPERVISION OF THE ELECTROMECHANICAL INSTALLATIONS OF THE NEW IT CENTER OF ALPHA BANK IN ALBANIA.
Scope of Works: The object of the given services includes the elaboration of the E/M installation designs and construction supervision. |